Seven stages, from first conversation to keys in hand

Building a luxury granny flat in Melbourne's east, south-east or on the Mornington Peninsula should never feel like guesswork. This is the exact process we follow on every project.

archsynth_image (22).png
Torquay 1.png
TORQUAY 2.jpg

Where the time actually goes

A lot of the granny flat project time is not construction. The build itself is 12-14 weeks; everything before it is design, testing, documentation and approvals. Where a planning permit is required, we run documentation alongside the council application rather than after it — which is where the shortest realistic timeline comes from.

7 Stages

Conference Room Setup

48 Hours

Accounting

$0 -First 2 Stages

AdobeStock_672112794 copper wedge x 4 (1).jpg
LIVING ROOM 3.jpg

12-14 Weeks on Site

Steel framed house.jpg

The same seven stages on every project.

What happens, what it costs, and how long it takes.

Our Process

01

Consultation & advice

A conversation, not a sales pitch — by phone or in our Kilsyth South showroom.

  • Designs matched to your block

  • Desktop site assessment

  • Title, overlays and easements checked

  • An early read on council

Complimentary · 30–60 minutes

02

Project proposal

A written proposal in your hands within two working days.

  • Estimated construction cost

  • Your options and upgrades, priced

  • Statutory fees for your council

  • Provisional items marked as provisional

Complimentary · Within 48 hours

03

Design & site report

Your project becomes real, and the site gets tested properly.

  • Preliminary working drawings

  • Soil classification and wind rating

  • Site feature survey

  • BAL assessment where required

  • Your Construction Manager assigned

From $8,000 + GST · 3–7 weeks

04

Council permits

Not every site needs a planning permit. Where yours does, we handle the whole application.

  • Application lodged and managed

  • Land Capability Assessment

  • Bushfire or flood overlay reports

  • Arborist report where required

  • Planning approval secured

$4,000–$10,000 + GST, where required · 12–24 weeks

05

Specification, selection & documentation

The enjoyable part — where a plan turns into your home.

  • Colours, finishes and fixtures chosen

  • Final construction drawings

  • Specification schedule

  • Structural engineering

  • 7-Star Energy Rating

From $7,500 + GST · Engineering $2,500–$4,000 · 5–10 weeks

06

Contract & building permit

Every inclusion, allowance and cost documented before you sign a thing.

  • HIA New Home Building Contract

  • Fixed inclusions and allowances

  • No open-ended items

  • Your building permit

  • A construction start date

5% deposit on signing · 2–8 weeks

​

Standard, not extra

Feature tiling, double-glazed windows, engineered flooring and a 7-star energy rating are standard across the range. Upgrades are named as upgrades, in writing, before you choose a thing.

Archsynth image (8).png

07

Construction

Six inspected stages, one point of contact, and a progress claim at each.

  • Base — stumps and base complete

  • Frame — floor, wall and roof

  • Lock-up — roof, walls, windows, doors

  • Fixing — linings, cabinetry, fixtures

  • Practical completion and handover

Progress claims at each stage · 12–14 weeks on site

ANGLESEA 2.png

25 +

Years building

Built under a Domestic Builder Unlimited registration, backed by Katana Building Services and more than 25 years of residential construction across Melbourne's east, south-east and the Mornington Peninsula.

DB-U

Every stage ends with something in your hands

Building should feel like progress you can hold. Every stage ends with something real — a proposal, your drawings, the site report, the contract — and nothing moves forward until you've seen it and you're happy. You'll always know where your home is up to, and who to call.